Finished Shed

April 24, 2009

The Climate Contolled shed is complete.  Notice how well it matches the existing house!!

Simulated brick

April 10, 2009

Ok you have to admit… This shed looks great!! The simulated brick stucco came out great. The drywall is up and textured.

Stucco scratch

April 3, 2009

The stucco scratch coat and the insulation were installed today. Tomorrow drywall starts.

Framing complete

March 5, 2009

The shed is now framed!

Slab poured

March 3, 2009

The slab is poured and ready for the framing crew!

Today we got the Deltona storage building started. The footers are dug and it’s ready for the termite treatment. We will pour the slab Monday.